Community Project Funding Requests and Associated Certifications
Community Project Funding Deck
City of Italy Water Wells Project
April 17, 2026
Proposed Recipient: City of Italy, Texas
Address of Recipient: PO Box 840, Italy, Texas 76651
Amount of Request: $391,962.54
Project Description and Statement of Public Benefit: Project Scope of Work
1. Pre-Construction Assessment
- Conduct a full downhole video inspection to evaluate casing integrity, screen condition, and evidence of corrosion, scaling, or structural failure.
- Perform baseline pump tests to document current yield, drawdown, and specific capacity.
- Complete electrical and control system assessment to determine compatibility with modern soft-start or variable-frequency drive (VFD) equipment.
2. Removal of Existing Equipment
- Pull the existing pump, motor, column pipe, shafting, and electrical wiring.
- Remove obsolete or damaged components for proper disposal in accordance with environmental regulations.
3. Structural Repairs and Casing Replacement
- Install new well casing or casing liners where deterioration or structural compromise is identified.
- Replace well screens, perforations, or gravel pack as required to restore structural integrity and prevent sand intrusion.
- Seal any voids or annular spaces in accordance with state well construction standards.
4. Pumping Equipment Replacement
- Install a new submersible or vertical turbine pump sized to meet system demand and hydraulic conditions.
- Replace the motor, column pipe, drop pipe, shafting, and all downhole wiring.
- Install new check valves, pitless adapters (if applicable), and sanitary seals.
5. Electrical and Power System Upgrades
- Replace outdated electrical wiring, conduit, and control panels.
- Install modern soft-start equipment and/or a variable-frequency drive (VFD) to improve energy efficiency, reduce mechanical stress, and enhance operational control.
- Upgrade surge protection, grounding, and safety disconnects to meet current electrical codes.
This project will have a positive impact on the city by increasing water capacity and availability. Will increase opportunity for development in and around city.
Click here to read full letter.